    • Lay the membrane or sheet so that the printed side is facing the fitter
    • Lay the sheet parallel or at a right angle to the rafters with an overlap of at least 10 cm
    • Ensure flush-processed bay insulation. There may be no cavities between the bay
      insulation and sheet/membrane. Visual check thanks to translucent character
    • Fit the membrane or sheet in a tension-free manner and avoid creases
    • Overlaps, component joints and penetrations must be made in an airtight manner by means of STEICO system accessories

    Processing in case of air-injected insulation

    • The distance between the clips to be used for fixing the vapour barrier in place on the
      supporting structure is max. 10 cm
    • The use of STEICO fibreboard strips or an additional lath along the rafter is recommended as an alternative
    • Before the introduction of the air-injected insulation, cross lathing must be arranged
      with a max. centre distance of 420 mm

    • Once the insulation has been injected, seal the injection holes in an airtight manner
      using STEICOmulti tape P stickers